Project name: Flannery Construction
Location: St. Paul, MN
Web site: www.flanneryconstruction.com
Architect: Roark Kramer Kosowski/DESIGN
Builder: Flannery Construction
Building size: 14,000 sf
Building use(s): Office, conference room, garage/workshop
Date of completion: November 2005
Ratings and awards:
Flannery Construction incorporated solar thermal space heating and domestic hot water into their new facility to match up with their goals and to apply for LEED certification. The building itself was designed with energy efficiency strategies, and provides a mix of office spaces, conference room, and a workshop in the garage area. The solar thermal array is mounted on the rooftop and one of the most visible systems in the Twin Cities as it sits just off of I-94 by Snelling Avenue. Currently this is the largest solar thermal installation in Minnesota. The collectors were flown in by crane as three separate arrays, preassembled in the factory by Solar Mining Co. This reduced some of the labor costs for connecting individual panels.
Effective energy use solutions:
Orientation: East west axis
Daylighting strategies:
Shading of structure:
Envelope:
Climate control systems:
Backup heating/power: Infloor radiant heating: Weil Mclain Ultra 310 Boiler with PhD reheating system internal combustion unit using natural gas: efficiency rating 95.6%
Total building energy use:
Solar system description and size:
Solar system cost: approximately $70,000
Financial incentives/donations:
Payback:
Date installation was completed: November 2005
System Designers: Innovative Power Systems (IPS) and Solar Mining Co.
Engineer: Gausman & Moore
Installer: Solar Mining Co. (sub contractor), IPS (General Contractor)
Estimated amount of energy delivered by system: approximately 2,000 therms per year
Percent of building's total energy use provided by solar: 6%
Modeling software: Energy modeling with engineering with Gausman & Moore
Flannery Construction's goal was to build its new headquarters in the most energy efficient manner possible with no more than a 5-7% increase in upfront costs and a cost savings pay-off within 7 years.
Flannery's healthy environment is greatly appreciated by employees, who all have access to daylight views from their workstations, and benefit from a controlled indoor climate through the building's in-floor radiant heat.
Flannery Construction has a commitment to using low-toxic finishes, sealants, carpet, and cleaning products. The company offers yoga to the employees two times a week and a place to shower and change afterwards. These steps were taken According to owner Gerry Flannery, "Employee health and well-being is directly correlated with productivity and retention."
This innovative construction company evaluated its own work flow before designing the office to minimize waste and to maximize efficiency, and was able to appropriate some great ideas from the many offices they have built for clients over the years.
Solar thermal panels work well in this climate.
Flannery recommended use of solar thermal in facilities that use a large amount of hot water (showers, swimming pools, etc), as well as incorporating a way to harness cooling energy from solar panels.
Other Sustainable Features: